What's Happening in Energy highlights the most interesting findings from public utility commission filings.
Subscribe to get these insights delivered straight to your inbox:
What's Happening in Energy — Nov 20
Powered by Halcyon
____
769 MW CCGT // CPCN Application // TeraWulf // Kentucky Power
Kentucky Power has re-applied to the Kentucky Public Service Commission (PSC) for a certificate of public convenience and necessity (CPCN) to build a 769 megawatt natural gas combined-cycle plant at its Big Sandy site in Lawrence County, KY. The utility withdrew its prior filling because, "due to a finalized agreement with TeraWulf, Inc., the amount of generation initially anticipated had doubled." The plant would use two General Electric Vernova (GEV) 7F.05 combustion turbines, cost approximately $2.81 billion (roughly $3,654/kW) and reach commercial operation in Q2 2031. The plant would serve TeraWulf's 1,000 MW Muskie data center campus in Boyd and Greenup counties, KY.
Muskie's load would ramp from 100 MW in October 2028 to 1,000 MW by October 2029.
Check out this bar chart of Kentucky Power’s PJM capacity position if the TeraWulf Electric Service Agreement (ESA) is approved. The ESA would more than double the utility’s existing load obligation.
Kentucky Power asks the PSC for a CPCN by March 1, 2027 for the $285 million Venator 765/345 kilovolt substation and for approval of a two-year bridge capacity agreement with AEP Generation Resources from June 1, 2029, through May 31, 2031.
CPCN application here
Cost estimates here
Turbine testimony here
Load ramp and bridge capacity testimony here
Kentucky Power also applied for approval of its ESA with TeraWulf in Case No. 2026-00323. The utility says the 20-year ESA would provide $2.1 billion in customer benefits and $100 million in residential rate credits over the life of the contract.
POLITICO’s Surge covered the project today, with Halcyon gas analyst Anna Seiple warning that in competitive markets, high new-plant costs could “trickle down to the rate payers.”
____
1,456 MW Gas Turbines // SpaceX // Texas // Air Permit Issued
The Texas Commission on Environmental Quality (TCEQ) has issued an air permit authorizing SpaceX to operate 1,456 megawatts of gas turbines in Cameron County, TX. The site will use eight GE Vernova 7E turbines, 18 Solar Turbines SMT-130 units, nine Mitsubishi FT8 turbines, six GE Vernova TM2500+Gen 6 turbines, and two GE Vernova TM2500+4 Gen 8 turbines.
____
Proposed VPP Regulations // FERC Order 2222 // Maryland
The Maryland Public Service Commission released proposed regulations governing how distributed energy resources (DERs) can participate in PJM’s wholesale markets. The rules would set out how utilities (Electric Distribution Companies), Distributed Energy Resource Aggregators (DERAs), and customers interact in the market. Comments are due December 16. Read Halcyon’s summary of the proposed regulations.
____
Two More Years to Comply // Ambient-Adjusted Line Ratings // New England // FERC
FERC granted New England transmission owners’ (TOs) request to extend their deadline for implementing ambient-adjusted line ratings (AAR) in their operations to December 31, 2028. AAR adjusts the flow limits of transmission lines based on weather conditions.
Under FERC Order 881, the TOs had until November 17, 2026, to implement AAR so that ISO New England could include the ratings in its day-ahead and real-time markets. Commissioner David Rosner dissented:
“I disagree with the majority’s conclusion that granting this waiver will not have undesirable consequences or harm third parties. Consumers are third parties, and depriving them of the benefits of more efficient transmission service for an additional two years is itself a significant and undesirable consequence.”
____
New CCGT Approved // 1,200 MW + 70 MW of Solar // West Virginia // Mon Power
The Public Service Commission of West Virginia approved Mon Power and Potomac Edison’s application for a Certificate of Public Convenience and Necessity (CPCN) to construct a 1,200 megawatt combined-cycle plant at Fort Martin ($2.48 billion), 70 megawatts of solar ($182 million), and a transmission line under one mile long ($20 million) to interconnect the project. The Commission also approved the applicants’ proposal to recover capital costs through a GP Surcharge before the project goes into service. Read Halcyon’s explanation of this surcharge. The companies estimated that these costs would add $470 million to the cost of the plants.
____
>16 GW of Growth // Large Loads // Q3 Report // Georgia Power
Georgia Power’s Q3 2026 large load economic development report shows that projects totaling 16,100 megawatts have either requested electric service or signed a contract with the utility. This includes load from data centers, crypto mining, manufacturing, and clean energy tech. Page 13 includes a table of the pipeline. Only projects in the “Contract for Electric Service” and “Request for Service” project stage are included in the 16--gigawatt figure. The remaining 80% of pipeline megawatts are still in “Technical Review.” One 3,500-megawatt “Data Center/Crypto” load in “Technical Review” has an in-service date of June 1, 2031.
____
Higher Peaks and Troughs // Monthly Operations Report // ERCOT
ERCOT’s October 2026 Monthly Operations Report includes a chart comparing 2026’s maximum and minimum monthly loads with 2025’s. From June through October, both the peaks and the troughs were higher in 2026 than in 2025. In October, the 81,487- megawatt peak load was 5,583 megawatts higher than in October 2025.
____
Getting Out of Town // Northern States Power // Wisconsin
Northern States Power Wisconsin (NSPW) applied to sell its electric and natural gas assets in Michigan to Upper Peninsula Power Company and SEMCO Energy Gas Company, respectively. NSPW argues that the sale will allow it to focus exclusively on Wisconsin, where it has more than 95% of its customers. The utility will also file applications with the Michigan Public Service Commission and FERC.
____
Non-Firm Service Coming to Chicagoland // ComEd // Illinois
Commonwealth Edison (ComEd) submitted a draft order asking the Illinois Commerce Commission (ICC) to approve its proposed Rider Non-Firm Retail Electric Service (Rider NFRES) and an expanded Rider Zero Standard Service (Rider ZSS). Rider NFRES would allow ComEd to interconnect large loads—or, as the utility calls them, “Large Demand Project Applicants and Customers” (LDPACs)—on a non-firm basis subject to curtailment. ComEd defines LDPAC’s as customers whose load reaches more than 50 megawatts within 10 years.
Rider ZSS would recover the full cost of distribution upgrades made to serve large loads and require those customers to provide a letter of credit.
____
Battery Storage RFP // Approved // Maine Public Utilities Commission
The Maine Public Utilities Commission approved the Request for Proposals (RFP) as proposed by the Department of Energy Resources (DOER). The RFP solicits up to 360 megawatts of battery storage from projects with at least three megawatts of nameplate capacity each. Awarded projects would enter into contracts with Maine utilities for a fixed bid price that is adjusted based on energy and capacity market revenues. DOER issued the RFP on November 19. Proposals are due three months after issuance (February 19, 2027), and provisional selection will occur roughly three months after that.
____
New Dockets of the Week
Responses Filed // FERC Show Cause Order
How could we not include these as dockets of the week? All ISO/RTOs have filed their responses to FERC’s Show Cause Order on large-load integration. Each has proposed its own approach to speeding up the integration of large loads onto its system.
PJM: for large loads of 50 megawatts or more at a single site; a new "Fast Energization Process" plus Firm Contract Demand and Non-Firm Contract Demand transmission services here
MISO: a Large Load Project Review (LLPR) process for loads of 50 MW or more, a Firm Service Step Up process and interim network integration transmission service here
CAISO: Flexible Interim Load Interconnection (FILI) to permit earlier energization while network upgrades are pending here
NYISO: new Large Load Integration Procedures with "Firm Withdrawal Service" and "Non-Firm Withdrawal Service" here
ISO-NE: three new local services: local firm contract demand service, local non-firm contract demand service, and local interim contract demand service here
Halcyon angle: Halcyon’s FERC Show Cause Tracker can help you make sense of the dizzying array of new dockets, market design proposals, and debates across ISO/RTOs. Learn more here.